Having individual staff members assigned to multiple simultaneous tasks is an efficient way to split tasks and get tasks accomplished more efficiently.

A) True
B) False

Correct Answer

verifed

verified

What are the impacts of resource-constrained scheduling?

Correct Answer

verifed

verified

Like leveling schedules, the limited res...

View Answer

When deciding which staff to team-up to work on work packages, factors to consider are:


A) Work habits.
B) Practical Experience.
C) Years of working in the company.
D) All of these choices are correct.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested.These activities are dependent on each other by _________ constraints.


A) Physical
B) Technical
C) Resource
D) Schedule
E) Time

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

What is the difference in project goals when using resource leveling on time-constrained projects and using it on resource-constrained projects?

Correct Answer

verifed

verified

In time-constrained projects the goal is...

View Answer

While balancing assignments, a project manager must also balance:


A) Overall project cost.
B) Talent development.
C) Earned value.
D) Work package slack.

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

When classifying projects, ________ constrained means that a specific resource is fixed and the duration of the project is flexible.

Correct Answer

verifed

verified

resource
Explanation: In sched...

View Answer

If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.

A) True
B) False

Correct Answer

verifed

verified

When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called


A) Outsourcing.
B) Redistribution of projects.
C) Project allocation.
D) Task sharing.
E) Referring.

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

All of the following are benefits of scheduling resources before project implementation EXCEPT


A) It allows time for considering reasonable options if resource constraints do exist.
B) The project completion date can be established.
C) Work packages can be time-phased.
D) It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) It ensures low network sensitivity.

F) C) and E)
G) A) and D)

Correct Answer

verifed

verified

The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.

A) True
B) False

Correct Answer

verifed

verified

__________ is a technique that can be used to solve the combinational problem of resource allocation.

Correct Answer

verifed

verified

Heuristics
Explanation: While ...

View Answer

Too many parallel activities for one individual is an example of a resource constraint.

A) True
B) False

Correct Answer

verifed

verified

Having too few programmers and too many engineers is an example of a people resource constraint.

A) True
B) False

Correct Answer

verifed

verified

In a resource-constrained project, the first priority in assigning resources is usually given to activities with the


A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

After constructing a project network based on technical constraints and reviewing resource requirements throughout the project, Anne realizes many peaks and valleys in regard to resource usage.At one point Anne needs 6 developers, but top management has made it very clear that she will not have access to more than 4.Classify Anne's project in terms of her scheduling problem.What are her options at this point?

Correct Answer

verifed

verified

Anne's project is classified as a resour...

View Answer

Technical constraints have been carefully considered when developing a project network.Which of the following is true at this point?


A) Resources have been assigned to each activity so they are adequate to complete the project on time.
B) Technical dependencies between activities are known.
C) The project completion date can be established.
D) The project is ready to be implemented.
E) All of these are true statements once technical constraints have been established.

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

Without a time-phased budget a good project schedule and cost control are impossible.

A) True
B) False

Correct Answer

verifed

verified

In a resource-constrained project, which of the following is most likely to be changed?


A) The completion date
B) The budget
C) Project quality
D) Resource levels
E) Scope creep

F) D) and E)
G) C) and E)

Correct Answer

verifed

verified

Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.

A) True
B) False

Correct Answer

verifed

verified

Showing 41 - 60 of 102